Low Voltage Main Distribution Board (MDB) Renovation
Discover how Alps Group modernized LEMO's MDB to meet the increased electricity demand caused by the expansion of operations and the installation of new equipment at the factory.

Context
LEMO, a world leader in the manufacture of precision connectors, has seen its production intensify since the construction of its Ecublens factory in 1987. With the addition of new machines, processing lines, and services, the factory’s electrical capacity was no longer sufficient, necessitating an update to the Low Voltage Main Distribution Board (MDB).
MDB Modernization to Increase Capacity
Ensure the electrical reliability of the factory and support LEMO’s continued growth.

Achievements
Alps Group took charge of the entire project:
- Electrical study, dimensioning, schematic design, and coordination with Romande Energie, suppliers, and electrical contractors
- Production of 11 Schneider Electric MDB cells, with workshop testing to ensure compliance and performance
- Dismantling of the old MDB and installation of the new system, even during the Christmas holiday period to minimize impact on production
- Final adjustments and verifications to ensure a smooth transition
Thanks to Alps Group’s expertise in engineering, hardware, industrial automation, and IT, the renovation was completed on time and within budget.